nvdaily.com link to home page

Traffic | Weather | Mobile Edition
Archives | Subscribe


Local News arrow RSW Jail

| 0 | 8 Comments

Regional jail work hits early snags

2012_09_27_Regional_JailW.jpg
Work continues on the regional jail site on Winchester Pike in Warren County. Rich Cooley/Daily

928RSWJailgraphic.jpg
Daily


Minor changes in plans cause costs to rise

By Alex Bridges -- abridges@nvdaily.com

FRONT ROYAL -- Costs to build the area's second regional jail started to rise early in the construction of the multi-million project.

The Rappahannock-Shenandoah-Warren Regional Jail Authority board at its meeting Thursday heard a report that designs for the nearly $80 million project ran afoul of some pipelines owned by Washington Gas.

Patton, Harris, Rust & Associates, performing the civil engineering for the jail, had to adjust plans for the project to compensate for gas lines on the site on U.S. 340-522 in Warren County.

Altering the plans cost an extra $11,000. The authority's owner representative, James Marstin, advised the board a project this size could run into some conflicts. Such issues can prompt a contractor to seek change orders which can result in the cost of a particular part of a project to increase.

"I guess that's a fair characterization, but you truly never really know where it's at, 'til you dig down and see it," said Marstin. "The gas line, it's not an exact science, especially something put in in the sixties."

PHR&A had to adjust the designs to compensate for gas lines buried at a shallower depth than thought. This resulted in changes to how the contractor dug near the gas lines to install culverts and other necessary features for the project. In one place, workers had to install a culvert under the pipeline, which required them to use hydraulic devices to excavate through rock, Marstin explained. Utility providers require construction elements such as drainage pipes and culverts not encroach on gas lines, according to Marstin. The consultant said he has to issue a change directive when the construction needs to go under the pipelines. The board could face delay claims should the authority not issue a change directive, Marstin said.

Representatives with the firms working on the project indicate the contractor, Howard Shockey & Sons, and Washington Gas, may share the blame for the need to change the design plans and the subsequent cost run-up. Tony Bell, with Moseley Architects, told the board the utility had given certain depth estimates to the design firm, some of which were off. Moseley also coordinated with Shockey regarding construction procedures, including the digging of pits to test the depth of the gas lines prior to any other building near the pipes. According to Bell, Shockey dug the test pits almost immediately prior to putting in the drainage culverts, which left little time to alter the design if possible. Moseley provided the information to PHR&A to avoid delay in the project.

"I'm painfully aware that our ability to coerce utilities [is] nonexistent," said John McCarthy, county administrator for Rappahannock County. "But it strikes me from the narrative that we're in this spot because the test pits ... weren't dug until just before we basically had to deal with the crossing, and was Shockey under no obligation to have done that a little bit sooner so we'd have a little more advance of a problem when we had it?"

"Actually, contract documents say the test pits were supposed to be dug as the first step of construction," said Ron Mislowski, of PHR&A.

Bell acknowledged it appeared Shockey had proceeded 45 to 60 days into the project before digging the test pits.

However, officials agreed the board couldn't know how much of a difference in the added cost earlier notice would have made.

Warren County Supervisor Dan Murray asked whether the authority could ask Shockey to share in the cost. Bell said they could try to see if Shockey would contribute to the cost.

McCarthy suggested the authority pass along a message to Shockey.

"We think they contributed to the severity of the problem that we had to deal with and we need to not have them make these kind of choices in the future," McCarthy said.




8 Comments



has anyone turned off their cell phones after seeing the signs telling them to turn them off when passing the jail site?

Boy, Increased costs. What a surprise. No one could have seen that happening. Good thing they prepared so well in advance and didn't just rush this project along to get it going before the courts could stop it. What a great benefit to the taxpayers.

It seems test holes to locate underground utility depths should be done during the design phase, not after the plans are done. I think Noah starting building the Ark before it began to rain.

This sounds a lot like the new end all super duper water treatment plant Woodstock built. In the words of council this plant will take us far into the future. Now lo & behold it needs to be upgraded to handle the amount of water because the design was off. Tax payers rejoice! You didn't have anything else to do with your money. Who is running these shows? Obama? If so, can we get a bail out package that doesn't need to be accounted for?

Washington Gas gave them an 'estimate of the depth' AND NOT an actual depth so don't blame them. They should have done the test drilling beforehand like it was required to do according to the contract. You don't build the roof ahead of the foundation and these guys were 45-60 days late in doing the required test pits. Therefore, they should pay for any 'overages' and not the taxpayers
What idiots!!!!!

Here, here! I'll motion as well that this bill should not be handed to the taxpayers. But as we know so well it doesn't usually work out that way.

Do the math. $10K is 0.0125% of the overall $80 million price. I'm not saying it won't eventually get out of control but right now it's very minor.

This is only the beginning. No one should be complaining unless you have supported Mark Prince and others who have tried to stop this.



Leave a comment

What do you think?

(You may use HTML tags for style)

Comments

Comments that are posted on nvdaily.com represent the opinion of the commenter and not the Northern Virginia Daily/nvdaily.com. If you feel that a comment is objectionable, please click on the Report Abuse link above and in your e-mail to us include the comment. We will review the reported comment and make a decision on deleting it if we feel that it contains inappropriate content.












Look Who 'Likes' nvdaily!



Daily readers: Click the "LIKE" button above to get Daily news and breaking news alerts on your Facebook page.

Activity & Recommendations

Local News Sections

Agency on Aging Agriculture Apple Blossom Festival Aviation Basye Berryville Boyce Breaking News Briefs Business Charities Civil War Clarke County Colleges Corrections Courthouse Notes: Permits, Transactions Courts & Legal News Crime & Public Safety Economy and Jobs Edinburg Education Edward N. Bell Election 2012 Entertainment Environment Fairs & Festivals Fire & Rescue Fishers Hill Fort Valley Frederick County Front Royal George Washington National Forest Guest Column Hard Times Health History Homes In The Spotlight Ledger Livestock Local Markets Maurertown Media Middletown Military & Veterans Moms Mt. Jackson New Market Page County Pets & Animals Politics Quicksburg Religion RSW Jail School News Shenandoah County Shenandoah Farms Volunteer Fire Department Star Tannery State Stephens City Steven A. Boyce Strasburg Toms Brook Traffic & Transportation Utilities Valley 911 Warren County Weather West Virginia Winchester Woodstock Year in Review




News | Sports | Business | Lifestyle | Obituaries | Opinion | Multimedia| Entertainment | Homes | Classifieds
Contact Us | NIE | Place a Classified | Privacy Policy | Subscribe

Copyright © The Northern Virginia Daily | nvdaily.com | 152 N. Holliday St., Strasburg, Va. 22657 | (800) 296-5137

nvdaily.com
Best Small Daily Newspaper in Virginia!


nvdaily.com | seeshenandoah.com