STREETSCAPE

Construction crews were milling the pavement along East King Street in Strasburg on Tuesday as part of the Streetscape project as it approaches the end of its second phase. Barring any unforeseen issues, Town Manager Wyatt Pearson said he is hoping crews will be able to pave the street by the end of the week. The project includes a crosswalk at the intersection of Massanutten and King streets. Pearson said the Virginia Department of Transportation has deemed the town responsible for the roughly $15,000 addition of a crosswalk to the construction plans after the town said it was mistakenly left off.